Dept. of Trans. PROGRESS Serial No. Contract No. 09-355-15-50 11-261714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 54% 11-SD-94-1.5/R13.4 Federal Project: NONE Progress payment No. 02 Payment period ending: 12-20-09 AMERICA WEST LANDSCAPE INC 15086 LA PALMA DRIVE CHINO CA 91710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 117,496.49 55,614.61 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 117,496.49 55,614.61 5. Mobilization 31,787.13 10,595.71 6. Total Work Completed 149,283.62 7. Deductions -3,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 146,283.62 64,210.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,210.32