Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-14-47 11-263004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 98% 11-SD-94-R13.2/R13.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 448,243.43 7,350.00 2.a. Extra Work 7,430.10 6,430.10 b. Adjustment Comp. -29.56 -29.56 3. Materials on Hand 4. Earned Subject to Retention 455,643.97 13,750.54 5. Mobilization 6. Total Work Completed 455,643.97 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -22,782.20 -687.53 b. Unsatisfactory Prog. -22,469.69 -687.52 c. Reduction after 95% Comp. 9. Total pay to Contractor 410,392.08 22,375.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,375.49