Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-005-13-48 11-263304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-IMP-8-R38.7/R39.3 NHPI-081(313) HPLU-6211(122) Progress payment No. 037 Payment period ending: 12-21-17 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,003,116.87 2,075.00 2. a. Extra Work 1,075,661.56 256,212.50 b. Adustment Comp. 76,759.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,155,538.24 258,287.50 5. Mobilization 900,000.00 0.00 6. Total Work Completed 13,055,538.24 7. Deductions -41,706.21 -27,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,013,832.03 231,287.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,287.50