Dept. of Trans. PROGRESS Serial No. Contract No. 13-324-15-07 11-264114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 30% 11-SD-163-1.4/ .0 Federal Project: BRLS-6211(89) Progress payment No. 03 Payment period ending: 11-20-13 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,310,409.50 614,245.00 2.a. Extra Work 10,298.53 6,056.97 b. Adjustment Comp. 3. Materials on Hand 22,032.00 22,032.00 4. Earned Subject to Retention 1,342,740.03 642,333.97 5. Mobilization 999,999.75 333,333.25 6. Total Work Completed 2,320,707.78 7. Deductions -4,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,338,739.78 974,667.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 974,667.22