Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-14-15 11-264114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 39% 11-SD-163-1.4/ .0 Federal Project: BRLS-6211(89) Progress payment No. 04 Payment period ending: 12-20-13 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,401,196.50 1,090,787.00 2.a. Extra Work 24,142.55 13,844.02 b. Adjustment Comp. 3. Materials on Hand 0.00 -22,032.00 4. Earned Subject to Retention 2,425,339.05 1,082,599.02 5. Mobilization 999,999.75 0.00 6. Total Work Completed 3,425,338.80 7. Deductions -14,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,411,338.80 1,072,599.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,072,599.02