Dept. of Trans. PROGRESS Serial No. Contract No. 14-111-11-45 11-264114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 77% 11-SD-163-1.4/ .0 Federal Project: BRLS-6211(89) Progress payment No. 08 Payment period ending: 04-20-14 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,678,527.20 2,547,114.75 2.a. Extra Work 511,497.03 109,313.12 b. Adjustment Comp. 3. Materials on Hand 25,054.86 -6,558.68 4. Earned Subject to Retention 10,215,079.09 2,649,869.19 5. Mobilization 1,333,333.00 0.00 6. Total Work Completed 11,523,357.23 7. Deductions -16,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,532,412.09 2,648,869.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,648,869.19