Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-15-37 11-264114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 88% 11-SD-163-1.4/ .0 Federal Project: BRLS-6211(89) Progress payment No. 09 Payment period ending: 05-20-14 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,247,240.20 1,568,713.00 2.a. Extra Work 529,794.50 18,297.47 b. Adjustment Comp. 3. Materials on Hand 8,505.00 -16,549.86 4. Earned Subject to Retention 11,785,539.70 1,570,460.61 5. Mobilization 1,333,333.00 0.00 6. Total Work Completed 13,110,367.70 7. Deductions -26,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,092,872.70 1,560,460.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,560,460.61