Dept. of Trans. PROGRESS Serial No. Contract No. 14-170-14-30 11-264114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 99% 11-SD-163-1.4/ .0 Federal Project: BRLS-6211(89) Progress payment No. 10 Payment period ending: 06-20-14 DISNEY CONSTRUCTION INC 859 COWAN RD #3 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,250,531.35 1,003,291.15 2.a. Extra Work 573,984.50 44,190.00 b. Adjustment Comp. 3. Materials on Hand 0.00 -8,505.00 4. Earned Subject to Retention 12,824,515.85 1,038,976.15 5. Mobilization 1,333,333.00 0.00 6. Total Work Completed 14,157,848.85 7. Deductions -17,000.00 9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,140,848.85 1,047,976.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,047,976.15