Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-14-05 11-264804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 90% 11-SD-5506 Federal Project: ACST-X073(85) PE-X073(85) Progress payment No. 08 Payment period ending: 04-20-09 CHOCTAW CONSTRUCTION COMPANY INC P O BOX 2308 RAMONA CA 92065 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 500,978.68 52,458.50 2.a. Extra Work 18,927.44 3,696.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 519,906.12 56,154.50 5. Mobilization 6. Total Work Completed 519,906.12 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 519,906.12 56,154.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,154.50