Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-14-45 11-264904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 50% 11-SD-5-R0.1/R0.3 Federal Project: ACST-005-1(604) PE-005-1(604) Progress payment No. 03 Payment period ending: 12-20-06 3 D ENTERPRISES INCORPORATED 2180 GARNET AVENUE STE 2C SAN DIEGO CA 92109 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,015.44 98,770.24 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 493,015.44 98,770.24 5. Mobilization 76,119.70 0.00 6. Total Work Completed 569,135.14 7. Deductions -26,877.02 5,107.98 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 542,258.12 103,878.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,878.22