Dept. of Trans. PROGRESS Serial No. Contract No. 14-111-14-30 11-2650A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 46% 11-SD-163-1.7/3.2 Federal Project: NONE Progress payment No. 16 Payment period ending: 04-20-14 ACCU CONSTRUCTION, INC. 1526 BROOKHOLLOW DR. STE. 76 SANTA ANA, CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 262,002.06 9,218.59 2.a. Extra Work 136,583.73 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 398,585.79 9,218.59 5. Mobilization 6. Total Work Completed 398,585.79 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 397,585.79 9,218.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,218.59