Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-08-16 11-2650A4 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 79% Location: Federal Project: 11-SD-163-1.7/3.2 NONE Progress payment No. 025 Payment period ending: 03-20-15 ACCU CONSTRUCTION, INC. 2098 S GRAND AVENUE, SUITE A SANTA ANA, CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 380,873.37 4,366.70 2. a. Extra Work 190,783.37 0.00 b. Adustment Comp. -66,600.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 505,056.74 4,366.70 5. Mobilization 6. Total Work Completed 505,056.74 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 505,056.74 6,366.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,366.70