Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-07-21 11-2650A4 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 85% Location: Federal Project: 11-SD-163-1.7/3.2 NONE Progress payment No. 027 Payment period ending: 05-20-15 ACCU CONSTRUCTION, INC. 2098 S GRAND AVENUE, SUITE A SANTA ANA, CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 421,629.24 13,100.10 2. a. Extra Work 190,783.37 0.00 b. Adustment Comp. -66,600.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 545,812.61 13,100.10 5. Mobilization 6. Total Work Completed 545,812.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 545,812.61 13,100.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,100.10