Dept. of Trans. PROGRESS Serial No. Contract No. 15-170-06-55 11-2650A4 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 88% Location: Federal Project: 11-SD-163-1.7/3.2 NONE Progress payment No. 028 Payment period ending: 06-20-15 ACCU CONSTRUCTION, INC. 2098 S GRAND AVENUE, SUITE A SANTA ANA, CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 434,244.16 12,614.91 2. a. Extra Work 190,783.37 0.00 b. Adustment Comp. -66,600.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 558,427.53 12,614.91 5. Mobilization 6. Total Work Completed 558,427.53 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 556,427.53 10,614.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,614.91