Dept. of Trans. PROGRESS Serial No. Contract No. 12-264-15-19 11-265304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 11-SD-15-0.5/M4.0 Federal Project: NH01-5017(E) Progress payment No. 07 Payment period ending: 09-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,529,256.04 99,019.69 2.a. Extra Work 93,075.51 77,296.33 b. Adjustment Comp. -30,481.05 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,591,850.50 176,316.02 5. Mobilization 284,450.00 0.00 6. Total Work Completed 4,876,300.50 7. Deductions -46,128.59 -12,320.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,830,171.91 163,996.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 163,996.02