Dept. of Trans. PROGRESS Serial No. Contract No. 06-171-14-14 11-265504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-5-R35.8/R36.3 Federal Project: ACIM-X073(73) G-X073(73) Progress payment No. 03 Payment period ending: 06-20-06 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 837,956.94 355,173.80 2.a. Extra Work 3,709.14 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 841,666.08 355,173.80 5. Mobilization 85,000.00 4,250.00 6. Total Work Completed 926,666.08 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 926,666.08 379,423.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 379,423.80