Dept. of Trans. PROGRESS Serial No. Contract No. 12-332-09-53 11-266104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 11-IMP-8-R0.0/R10.0 Federal Project: ACIM-082(103) Progress payment No. 08 Payment period ending: 11-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,092,224.68 255,618.15 2.a. Extra Work 77,417.12 0.00 b. Adjustment Comp. -8,426.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,161,215.31 255,618.15 5. Mobilization 1,347,600.00 0.00 6. Total Work Completed 13,508,815.31 7. Deductions -3,065,268.51 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,443,546.80 253,618.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 253,618.15