Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-030-10-36 11-266504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-94-30.0/38.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 12-29-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,416,417.10 26,396.31 2.a. Extra Work 21,255.87 21,255.87 b. Adjustment Comp. -30,469.14 -30,469.14 3. Materials on Hand 4. Earned Subject to Retention 1,407,203.83 17,183.04 5. Mobilization 75,000.00 0.00 6. Total Work Completed 1,482,203.83 7. Deductions -12,632.50 -12,632.50 8. a.Contract Retentions -69,501.04 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 69,501.04 69,501.04 9. Total pay to Contractor 1,469,571.33 74,051.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74,051.58