Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-07-20 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 50% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-20-08 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,103,655.90 2,878,891.53 2.a. Extra Work 254,654.11 62,646.05 b. Adjustment Comp. 92,685.14 0.00 3. Materials on Hand 569,330.88 40,656.10 4. Earned Subject to Retention 8,020,326.03 2,982,193.68 5. Mobilization 1,505,750.00 0.00 6. Total Work Completed 8,956,745.15 7. Deductions -847,907.30 -826,939.77 8. a.Contract Retentions -401,016.30 -67,224.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,277,152.43 2,088,029.72 10. Reduction Amt to Escrow 11. Payment to Escrow 401,010.00 12. Net Pymt. this Estimate 2,088,029.72