Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-14-10 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 68% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 11 Payment period ending: 01-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,338,282.57 430,026.38 2.a. Extra Work 535,007.67 3,070.75 b. Adjustment Comp. 90,207.21 -5,089.83 3. Materials on Hand 461,810.20 -52,757.07 4. Earned Subject to Retention 12,425,307.65 375,250.23 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 13,548,497.45 7. Deductions -57,992.67 -1,798.60 8. a.Contract Retentions -621,265.38 -18,762.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,331,049.60 354,689.12 10. Reduction Amt to Escrow 11. Payment to Escrow 621,260.00 12. Net Pymt. this Estimate 354,689.12