Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-25 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 75% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 12 Payment period ending: 02-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,951,937.84 613,655.27 2.a. Extra Work 544,540.85 9,533.18 b. Adjustment Comp. 78,807.06 -11,400.15 3. Materials on Hand 408,695.24 -53,114.96 4. Earned Subject to Retention 12,983,980.99 558,673.34 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 14,160,285.75 7. Deductions -57,992.67 0.00 8. a.Contract Retentions -649,199.05 -27,933.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,861,789.27 530,739.67 10. Reduction Amt to Escrow 11. Payment to Escrow 649,190.00 12. Net Pymt. this Estimate 530,739.67