Dept. of Trans. PROGRESS Serial No. Contract No. 09-083-14-17 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 82% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 13 Payment period ending: 03-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,599,157.23 647,219.39 2.a. Extra Work 584,890.08 40,349.23 b. Adjustment Comp. 1,560.61 -77,246.45 3. Materials on Hand 350,776.11 -57,919.13 4. Earned Subject to Retention 13,536,384.03 552,403.04 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 14,770,607.92 7. Deductions -48,329.83 9,662.84 8. a.Contract Retentions -676,819.20 -27,620.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,396,235.00 534,445.73 10. Reduction Amt to Escrow 11. Payment to Escrow 676,810.00 12. Net Pymt. this Estimate 534,445.73