Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-14-13 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 19 Payment period ending: 10-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,044,242.34 72,389.02 2.a. Extra Work 1,001,222.42 55,534.09 b. Adjustment Comp. 19,079.03 2,540.25 3. Materials on Hand 4. Earned Subject to Retention 16,064,543.79 130,463.36 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 17,649,543.79 7. Deductions -248,916.50 0.00 8. a.Contract Retentions -803,227.19 -6,523.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,597,400.10 123,940.19 10. Reduction Amt to Escrow 11. Payment to Escrow 803,220.00 12. Net Pymt. this Estimate 123,940.19