Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-14-53 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 100% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 20 Payment period ending: 11-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,200,046.23 155,803.89 2.a. Extra Work 1,020,027.12 18,804.70 b. Adjustment Comp. -11,428.93 -30,507.96 3. Materials on Hand 4. Earned Subject to Retention 16,208,644.42 144,100.63 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 17,793,644.42 7. Deductions -242,916.50 6,000.00 8. a.Contract Retentions -810,432.22 -7,205.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,740,295.70 142,895.60 10. Reduction Amt to Escrow 11. Payment to Escrow 810,430.00 12. Net Pymt. this Estimate 142,895.60