Dept. of Trans. PROGRESS Serial No. Contract No. 10-053-14-42 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 23 Payment period ending: 02-20-10 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,352,033.68 16,201.00 2.a. Extra Work 1,301,743.41 61,791.11 b. Adjustment Comp. -9,772.97 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,644,004.12 77,992.11 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 18,229,004.12 7. Deductions -238,916.50 1,000.00 8. a.Contract Retentions -832,200.21 -3,899.61 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,157,887.41 75,092.50 10. Reduction Amt to Escrow 11. Payment to Escrow 832,200.00 12. Net Pymt. this Estimate 75,092.50