Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-110-17-40 11-267304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-52-7.4/13.3 Federal Project: NONE Progress payment No. 37 Payment period ending: 01-03-11 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 02396 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,456,857.21 2,130.50 2.a. Extra Work 2,326,010.19 71,646.60 b. Adjustment Comp. 137,995.70 -2,566.46 3. Materials on Hand 4. Earned Subject to Retention 17,920,863.10 71,210.64 5. Mobilization 1,585,000.00 0.00 6. Total Work Completed 19,505,863.10 7. Deductions -28,550.49 -18,000.00 8. a.Contract Retentions -892,482.62 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 892,482.62 892,482.62 9. Total pay to Contractor 19,477,312.61 945,693.26 10. Reduction Amt to Escrow -892,480.00 -892,480.00 11. Payment to Escrow 892,480.00 12. Net Pymt. this Estimate 53,213.26