Dept. of Trans. FINAL Serial No. Contract No. 09-021-09-40 11-267404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-78-35.1/ .0 Federal Project: ACST-P078(106) PHG-P078(106) Progress payment No. 10 Payment period ending: 04-28-08 DALEY CORPORATION 5370 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 649,369.56 150.54 2.a. Extra Work 49,924.58 0.00 b. Adjustment Comp. 10,484.13 0.00 3. Materials on Hand 4. Earned Subject to Retention 709,778.27 150.54 5. Mobilization 49,440.00 0.00 6. Total Work Completed 759,218.27 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 759,218.27 150.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150.54