Dept. of Trans. PROGRESS Serial No. Contract No. 06-114-14-27 11-268304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 58% 11-SD-5-R0.1/ .0 Federal Project: CBP-005-1(601) Progress payment No. 02 Payment period ending: 04-20-06 F C BUSINESS SYSTEMS INC 2726 ESCALA CIRCLE SAN DIEGO CA 92108 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,039.00 13,239.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 29,039.00 13,239.00 5. Mobilization 10,500.00 3,500.00 6. Total Work Completed 39,539.00 7. Deductions -6,949.90 -2,159.90 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,589.10 14,579.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,579.10