Dept. of Trans. PROGRESS Serial No. Contract No. 07-114-07-40 11-268404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 9% 11-SD-56-0.7/2.4 Federal Project: ACST-P056(3) PHG-P056(3) Progress payment No. 01 Payment period ending: 04-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,823.16 328,823.16 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 328,823.16 328,823.16 5. Mobilization 178,582.50 178,582.50 6. Total Work Completed 507,405.66 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 507,405.66 507,405.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 507,405.66