Dept. of Trans. PROGRESS Serial No. Contract No. 07-204-14-13 11-268404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 63% 11-SD-56-0.7/2.4 Federal Project: ACST-P056(3) PHG-P056(3) Progress payment No. 04 Payment period ending: 07-20-07 SIM J HARRIS INC 4375 JUTLAND DR., STE 200 SAN DIEGO CA 92117 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 703,712.20 169,975.12 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 703,712.20 169,975.12 5. Mobilization 226,204.50 0.00 6. Total Work Completed 929,916.70 7. Deductions -42,493.78 -42,493.78 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 887,422.92 127,481.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 127,481.34