Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-14-25 11-268404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-56-0.7/2.4 Federal Project: ACST-P056(3) PHG-P056(3) Progress payment No. 07 Payment period ending: 10-20-07 SIM J HARRIS INC 4375 JUTLAND DR., STE 200 SAN DIEGO CA 92117 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,077,750.44 327,325.54 2.a. Extra Work 18,368.30 9,669.10 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,096,118.74 336,994.64 5. Mobilization 238,110.00 0.00 6. Total Work Completed 2,334,228.74 7. Deductions -93,455.78 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 105,541.19 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,240,772.96 442,535.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 442,535.83