Dept. of Trans. PROGRESS Serial No. Contract No. 14-055-14-58 11-269304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 82% 11-SD-56-0.0/8.9 Federal Project: STP-X073(101) Progress payment No. 12 Payment period ending: 02-20-14 DBX INC 42024 AVENIDA ALVARADO SUITE TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,930,292.99 261,878.52 2.a. Extra Work 257,563.69 35,136.23 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,187,856.68 297,014.75 5. Mobilization 100,000.00 0.00 6. Total Work Completed 4,287,856.68 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,287,856.68 297,014.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,014.75