Dept. of Trans. PROGRESS Serial No. Contract No. 08-234-14-49 11-270604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 95% 11-SD-8-R26.5/R26.8 Federal Project: ACIM-4125(4) Progress payment No. 04 Payment period ending: 08-20-08 NEWPORT GRADING INC 3046 EVERWOOD DRIVE RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 172,483.42 28,563.22 2.a. Extra Work 42,444.92 42,084.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 214,928.34 70,647.22 5. Mobilization 14,000.00 0.00 6. Total Work Completed 228,928.34 7. Deductions -7,636.07 6,793.84 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 221,292.27 77,441.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,441.06