Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-14-37 11-272304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 80% 11-SD-76-14.3/14.9 Federal Project: ER-4132(4) Progress payment No. 01 Payment period ending: 11-20-08 SIM ENGINEERING INC 3658 PALOMAR DRIVE FALLBROOK CA 92028 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,260.00 90,260.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 90,260.00 90,260.00 5. Mobilization 6. Total Work Completed 90,260.00 7. Deductions -9,026.00 -9,026.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 81,234.00 81,234.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,234.00