Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-068-07-10 11-275004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-115-R3.1/21.2 Federal Project: ACST-S115(9) P-S115(9) Progress payment No. 09 Payment period ending: 05-06-08 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,624,922.03 0.00 2.a. Extra Work 130,692.52 0.00 b. Adjustment Comp. 65,484.88 -515.06 3. Materials on Hand 4. Earned Subject to Retention 3,821,099.43 -515.06 5. Mobilization 300,000.00 0.00 6. Total Work Completed 4,121,099.43 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,121,099.43 4,484.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,484.94