Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-13-57 11-275204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 80% 11-IMP-98-21.8/31.3 Federal Project: STP-P098(24) Progress payment No. 06 Payment period ending: 12-20-13 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,271,889.03 354,799.48 2.a. Extra Work 103,117.40 76,133.46 b. Adjustment Comp. -10,302.71 -10,302.71 3. Materials on Hand 4. Earned Subject to Retention 1,364,703.72 420,630.23 5. Mobilization 304,000.00 0.00 6. Total Work Completed 1,668,703.72 7. Deductions -17,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,651,703.72 420,630.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 420,630.23