Dept. of Trans. PROGRESS Serial No. Contract No. 14-055-10-55 11-275204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 80% 11-IMP-98-21.8/31.3 Federal Project: STP-P098(24) Progress payment No. 08 Payment period ending: 02-20-14 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,271,889.03 0.00 2.a. Extra Work 133,272.50 12,380.54 b. Adjustment Comp. -10,302.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,394,858.82 12,380.54 5. Mobilization 304,000.00 0.00 6. Total Work Completed 1,698,858.82 7. Deductions -18,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,680,858.82 17,380.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,380.54