Dept. of Trans. PROGRESS Serial No. Contract No. 14-143-10-16 11-275204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 90% 11-IMP-98-21.8/31.3 Federal Project: STP-P098(24) Progress payment No. 10 Payment period ending: 05-20-14 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,571,793.43 1,299,904.40 2.a. Extra Work 144,671.79 9,513.05 b. Adjustment Comp. -10,302.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,706,162.51 1,309,417.45 5. Mobilization 320,000.00 16,000.00 6. Total Work Completed 3,026,162.51 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,024,162.51 1,323,417.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,323,417.45