Dept. of Trans. PROGRESS Serial No. Contract No. 14-170-14-40 11-275204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 99% 11-IMP-98-21.8/31.3 Federal Project: STP-P098(24) Progress payment No. 11 Payment period ending: 06-20-14 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,949,690.05 377,896.62 2.a. Extra Work 211,373.70 66,701.91 b. Adjustment Comp. -10,302.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,150,761.04 444,598.53 5. Mobilization 320,000.00 0.00 6. Total Work Completed 3,470,761.04 7. Deductions -7,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,463,761.04 439,598.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 439,598.53