Dept. of Trans. PROGRESS Serial No. Contract No. 15-236-13-51 11-275504 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 48% Location: Federal Project: 11-SD-67-R0.0/R5.9 STPN-P067-7(71) Progress payment No. 004 Payment period ending: 08-20-15 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO, CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,430,111.88 1,061,974.73 2. a. Extra Work 14,011.21 10,786.21 b. Adustment Comp. -163,749.28 -95,604.56 3. Materials on Hand 4. Earned Subject to Retention 2,280,373.81 977,156.38 5. Mobilization 950,000.00 200,000.00 6. Total Work Completed 3,230,373.81 7. Deductions -7,035.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,223,338.81 1,174,156.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,174,156.38