Dept. of Trans. PROGRESS Serial No. Contract No. 15-260-14-28 11-275504 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 59% Location: Federal Project: 11-SD-67-R0.0/R5.9 STPN-P067-7(71) Progress payment No. 005 Payment period ending: 09-20-15 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO, CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,007,998.88 1,577,887.00 2. a. Extra Work 14,821.58 810.37 b. Adustment Comp. -271,102.16 -107,352.88 3. Materials on Hand 92,485.12 92,485.12 4. Earned Subject to Retention 3,844,203.42 1,563,829.61 5. Mobilization 950,000.00 0.00 6. Total Work Completed 4,701,718.30 7. Deductions -14,517.50 -7,482.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,779,685.92 1,556,347.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,556,347.11