Dept. of Trans. PROGRESS Serial No. Contract No. 15-295-13-05 11-275504 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 70% Location: Federal Project: 11-SD-67-R0.0/R5.9 STPN-P067-7(71) Progress payment No. 006 Payment period ending: 10-20-15 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO, CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,191,185.13 1,183,186.25 2. a. Extra Work 15,071.58 250.00 b. Adustment Comp. -319,878.79 -48,776.63 3. Materials on Hand 193,920.41 101,435.29 4. Earned Subject to Retention 5,080,298.33 1,236,094.91 5. Mobilization 950,000.00 0.00 6. Total Work Completed 5,836,377.92 7. Deductions -18,517.50 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,011,780.83 1,232,094.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,232,094.91