Dept. of Trans. PROGRESS Serial No. Contract No. 15-323-13-45 11-275504 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 39% Location: Federal Project: 11-SD-67-R0.0/R5.9 STPN-P067-7(71) Progress payment No. 007 Payment period ending: 11-20-15 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO, CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,445,864.63 254,679.50 2. a. Extra Work 33,653.88 18,582.30 b. Adustment Comp. -319,878.79 0.00 3. Materials on Hand 190,426.67 -3,493.74 4. Earned Subject to Retention 5,350,066.39 269,768.06 5. Mobilization 950,000.00 0.00 6. Total Work Completed 6,109,639.72 7. Deductions -24,517.50 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,275,548.89 263,768.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 263,768.06