Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-07-36 11-275504 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 79% Location: Federal Project: 11-SD-67-R0.0/R5.9 STPN-P067-7(71) Progress payment No. 008 Payment period ending: 12-20-15 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO, CA 92192-9000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,960,370.68 514,506.05 2. a. Extra Work 48,793.91 15,140.03 b. Adustment Comp. -338,309.25 -18,430.46 3. Materials on Hand 96,102.63 -94,324.04 4. Earned Subject to Retention 5,766,957.97 416,891.58 5. Mobilization 1,000,000.00 50,000.00 6. Total Work Completed 6,670,855.34 7. Deductions -20,517.50 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -41,689.16 -41,689.16 c. Reduction after 95% Comp. 9. Total pay to Contractor 6,704,751.31 429,202.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 429,202.42