Dept. of Trans. PROGRESS Serial No. Contract No. 06-265-15-09 11-276304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 64% 11-SD-5-R14.7/R15.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-06 LIGHTNING FENCE CO 13950 OLIVE CREST WAY POWAY CA 92064 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 327,793.63 237,688.86 2.a. Extra Work 1,748.00 1,748.00 b. Adjustment Comp. 14,535.50 14,535.50 3. Materials on Hand 4. Earned Subject to Retention 344,077.13 253,972.36 5. Mobilization 6. Total Work Completed 344,077.13 7. Deductions -20,738.00 -16,678.00 8. a.Contract Retentions -17,203.86 -8,256.93 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 306,135.27 229,037.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,037.43