Dept. of Trans. PROGRESS Serial No. Contract No. 08-084-14-19 11-276404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 61% 11-SD-5-6.3/R53.5 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-20-08 ARBORWORKS INC 11875 DUBLIN BLVD SUITE C 152 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 362,865.00 113,021.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 362,865.00 113,021.00 5. Mobilization 5,500.00 0.00 6. Total Work Completed 368,365.00 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -18,143.25 -5,651.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 349,221.75 107,369.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,369.95