Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-343-08-36 11-276614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-111-R4.7/T8.2 Federal Project: NONE Progress payment No. 07 Payment period ending: 06-22-09 ORTIZ ASPHALT PAVING INC P O BOX 883 COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,001,853.98 0.00 2.a. Extra Work 49,724.77 0.00 b. Adjustment Comp. -244,708.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,806,869.79 0.00 5. Mobilization 3,236.61 0.00 6. Total Work Completed 1,810,106.40 7. Deductions -141,719.83 1,294.17 8. a.Contract Retentions -101,232.36 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 101,232.36 0.00 9. Total pay to Contractor 1,668,386.57 1,294.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,294.17