Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-11-01 11-276904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 45% 11-SD-94-39.0/52.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 313,083.48 261,695.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 313,083.48 261,695.34 5. Mobilization 112,500.00 112,500.00 6. Total Work Completed 425,583.48 7. Deductions 8. a.Contract Retentions -31,308.35 -26,169.54 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 394,275.13 348,025.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 348,025.80