Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-14-21 11-277004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 27% 11-SD-78-0.0/3.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-07 ORTIZ ASPHALT PAVING INC P O BOX 883 COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 477,148.62 477,148.62 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 477,148.62 477,148.62 5. Mobilization 42,242.86 42,242.86 6. Total Work Completed 519,391.48 7. Deductions 8. a.Contract Retentions -23,857.43 -23,857.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 495,534.05 495,534.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 495,534.05