Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-14-20 11-277604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 18% 11-IMP-78-15.5/41.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-09 MANHOLE ADJUSTING CONTRACTORS INC 9500 BEVERLY ROAD PICO RIVERA CA 90660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 252,460.93 252,460.93 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 252,460.93 252,460.93 5. Mobilization 80,000.00 80,000.00 6. Total Work Completed 332,460.93 7. Deductions -640.50 -640.50 8. a.Contract Retentions -25,246.09 -25,246.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 306,574.34 306,574.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,574.34